Question: Question 2 options: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 20 32
Question 2 options:
|
|
|
|
| TIMES (days) |
|
| Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
| A | 1 | 2 | 20 | 32 | 56 |
| B | 1 | 3 | 19 | 25 | 37 |
| C | 2 | 5 | 16 | 40 | 64 |
| D | 3 | 4 | 31 | 40 | 67 |
| E | 4 | 5 | 16 | 34 | 52 |
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 34 Standard Deviation = 6 Activity Bte =
Standard Deviation =
Activity Cte =
Standard Deviation =
Activity Dte =
Standard Deviation =
Activity Ete =
Standard Deviation = 6 Path 1 2 5 Mean Time =
Standard Deviation =10 Path 1 3 4 5 Mean Time =
Standard Deviation =