Question: The information for a project is given in the Table below (time in weeks): Activity Immediate predecessors Activity time (t) A - 4 B A
The information for a project is given in the Table below (time in weeks):
| Activity | Immediate predecessors | Activity time (t) |
| A | - | 4 |
| B | A | 3 |
| C | A | 3 |
| D | C | 3 |
| E | D | 1 |
| F | B | 2 |
| G | B | 1 |
| H | G | 4 |
| I | F | 5 |
| J | H, I | 1 |
| K | H, I | 1 |
| l | J, K | 1 |
- Draw a network for this project
- Determine the critical path
- Determine the earliest and latest activity times
- Determine slack time for each activity