Question: Question 2: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 23 32 59
Question 2:
| TIMES (days) | |||||
| Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
| A | 1 | 2 | 23 | 32 | 59 |
| B | 1 | 3 | 22 | 28 | 40 |
| C | 2 | 5 | 12 | 24 | 60 |
| D | 3 | 4 | 30 | 39 | 66 |
| E | 4 | 5 | 15 | 33 | 51 |
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 35 Standard Deviation = 6
Activity Bte = Standard Deviation =
Activity Cte = Standard Deviation =
Activity Dte = Standard Deviation =
Activity Ete = Standard Deviation = 6 Path 1 2 5 Mean Time = Standard Deviation =10 Path 1 3 4 5 Mean Time = Standard Deviation =