Question: Question 4 options: TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 26 38
Question 4 options:
| TIMES (days) |
| ||||
| Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
| A | 1 | 2 | 26 | 38 | 62 |
| B | 1 | 3 | 16 | 22 | 34 |
| C | 2 | 5 | 14 | 26 | 62 |
| D | 3 | 4 | 32 | 44 | 68 |
| E | 4 | 5 | 15 | 27 | 51 |
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity Ate = 40 Standard Deviation = 6 Activity Bte =
Standard Deviation =
Activity Cte =
Standard Deviation =
Activity Dte =
Standard Deviation =
Activity Ete =
Standard Deviation = 6 Path 1 2 5 Mean Time =
Standard Deviation =10 Path 1 3 4 5 Mean Time =
Standard Deviation =