Question: Question 2 You are managing a construction project with a three-year duration. After one year, you find that the project is behind the schedule, and
Question 2 You are managing a construction project with a three-year duration. After one year, you find that the project is behind the schedule, and it would need to be extended by at least six months. This would cost your company at least $200,000 due to delayed project delivery. What can you do to deliver the project within three years? Please list at least three options and briefly explain what needs to be done in each option? 3 marks