Question: Question 3: The table below gives the optimistic, most likely and pessimistic time estimates in days for all activities in a project. Expected Activity Variance

Question 3: The table below gives the optimistic,
Question 3: The table below gives the optimistic, most likely and pessimistic time estimates in days for all activities in a project. Expected Activity Variance Activity duration (PERT) m o 0 SD 5 6 12 9 AllesLU- B D E F G H 1 Total 9 18 12 8 S -0-00 - 1900 1919 8 16 9 7 + 6 S 9 3 1 8 -Calculate the expected duration for each activity on the project. - What is the variance for each single activity on the project. - What is the standard deviation of the project