Question: QUESTION 4 Problem 3 (25 pts) Task Normal time (days) Crash time (days) Normal Cost ($) Crash Cost ($) Predecessor(s) a 20 12 50 70

QUESTION 4

Problem 3 (25 pts)

Task Normal time (days) Crash time (days) Normal Cost ($) Crash Cost ($) Predecessor(s)
a 20 12 50 70
b 14 12 60 80
c 7 6 70 160 b
d 2 1 20 50 a, c
e 3 2 200 300 a, c
f 8 5 100 200 b
g 5 4 50 100 d
h 6 3 60 180 e, f
a. Draw a AON network diagram for the project. (5 pts)
b. Mark the critical path and state its length using normal time. (5 pts)
c. Calculate crash cost per period for all project activities. (5 pts)
d. The project has to be completed 1 day earlier. Which task should be crashed first? Explain why.
e. Crash the project by 2 days with the least cost. Which activities have to be crashed? How much is additional cost for this crash

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!