Question: QUESTION 4 Problem 3 (25 pts) Task Normal time (days) Crash time (days) Normal Cost ($) Crash Cost ($) Predecessor(s) a 20 12 50 70
| QUESTION 4 | |||||
| Problem 3 (25 pts) | |||||
| Task | Normal time (days) | Crash time (days) | Normal Cost ($) | Crash Cost ($) | Predecessor(s) |
| a | 20 | 12 | 50 | 70 | |
| b | 14 | 12 | 60 | 80 | |
| c | 7 | 6 | 70 | 160 | b |
| d | 2 | 1 | 20 | 50 | a, c |
| e | 3 | 2 | 200 | 300 | a, c |
| f | 8 | 5 | 100 | 200 | b |
| g | 5 | 4 | 50 | 100 | d |
| h | 6 | 3 | 60 | 180 | e, f |
| a. Draw a AON network diagram for the project. (5 pts) | |||||
| b. Mark the critical path and state its length using normal time. (5 pts) | |||||
| c. Calculate crash cost per period for all project activities. (5 pts) | |||||
| d. The project has to be completed 1 day earlier. Which task should be crashed first? Explain why. | |||||
| e. Crash the project by 2 days with the least cost. Which activities have to be crashed? How much is additional cost for this crash |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock