Question: QUESTION 4 The critical path for the network activities shown below is with duration Activity Duration Immediate Predecessors A 10 B 8 C 2 A

QUESTION 4 The critical path for the network activities shown below is with duration Activity Duration Immediate Predecessors A 10 B 8 C 2 A D 4 A E 5 B,C. D O B-E; 13 O A-D-E; 19 O A-C, 12 O A-B-C-D-E, 29 O none of the above