Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 10 B 8 C 4 A

The critical path for the network activities shown below is ________ with duration ________.

Activity

Duration

Immediate

Predecessors

A

10

B

8

C

4

A

D

2

A

E

6

B, C, D

A. A-B-D-E; 26

B. A-C-E; 20

C. B-E; 14

D. A-D-E; 18

E. None of the above.