Question: QUESTION TWO [ 1 5 ] Using the information in the table below, assuming that the project team k a standard working week ( 5
QUESTION TWO
Using the information in the table below, assuming that the project team k a standard
working week working days in week and possible:
Task Description Duration
Working Days
Predecessors
A Requirement Analysis
B Systems Design A
C Programming B
D Telecoms B
E Hardware Installation B
F Integration C D
G System Testing E F
H Documentation G
I TrainingSupport H
J Handover and GoLive H
K Maintenance I, J
Determine the critical path of the project.
Calculate the planned duration of the project in weeks.
Identify any noncritical tasks and the float free slack on each.
Assume that you were the project manager for the King Shaka International Airport project. Illustrate clearly the process you would have engaged in to manage successfully the scope of this successful project
Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. The key benefit of this process is that it provides the basis for defining and managing the project scope including product scope. Key people from Turner & Townsend UK visited the Ilembe consortium in early to understand the principle requirements Critically appraise at least FIVE toolstechniques that Turner & Townsend together with the Ilembe consortium could have used to collect requirements.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock