Question: QUESTION 5 Given is a CPM project network diagram as shown below. F F H E Start E End B D Activity day Start 0

QUESTION 5 Given is a CPM project network diagram

QUESTION 5 Given is a CPM project network diagram as shown below. F F H E Start E End B D Activity day Start 0 A 5 B 8 3 D 5 E 6 F 8 G 3 H 4 End 0 a) The Project Completion time = days. b) The Earliest Start time. ES. of Activity G= days. c) The Latest Finish time. LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in answer as: ABCD)