Question: QUESTION 5 Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0
QUESTION 5
-
Given is a CPM project network diagram as shown below.
a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in answer as: ABCD)Activity
Start
A
B
C
D
E
F
G
H
End
day
0
4
3
7
5
2
5
8
4
0