Question: Question 7 : AOA and Gantt chart Analysis. ( 7 marks ) A . What are the late finish for activity A , D and

Question 7: AOA and Gantt chart Analysis. (7 marks) A. What are the late finish for activity A,D and F in the network shown in the diagram? (3marks) Use the Gantt chart and activity list to answer the questions that follow. B. Use the Gantt chart and activity list to determine which resource is used the least. (2 marks) C. Use the Gantt chart and activity list to determine which resource is used the most. (2 marks)