Question: QUESTION 9 Given the following project activities. 12 coco 10 20 TIME IN DAYS Activity Optimistic Most Likely Pessimistic A 10 14 B 8 6

QUESTION 9 Given the following project
QUESTION 9 Given the following project activities. 12 coco 10 20 TIME IN DAYS Activity Optimistic Most Likely Pessimistic A 10 14 B 8 6 D 8 E 17 30 The variance of activity A is (in days) 0.667 0.111 0.444 O 12 28 15 QUESTION 10 Given the following project activities C S and Submit to save and submi