Question: Question content area Part 1 Draw an activity chart for a machine operator with the following operation. The relevant times are as follows: Prepare mill

Question content area
Part 1
Draw an activity chart for a machine operator with the following operation. The relevant times are as follows:
Prepare mill for loading(cleaning, oiling, and so on)
0.50 min
Load mill
1.75 min
Mill operating(cutting material)
2.25 min
Unload mill
0.75 min
Part 2
Plot all required processes and their relevant times on the chart. Choose the correct graph below.
A.
1
2
3
4
5
6
1
2
3
4
5
6
1
2
3
4
5
6
Time
Operator
Time
Machine
Time
Prepare Mill
Idle
Idle
Unload Mill
Load Mill
Mill
Operating
(Cutting
Material)
Idle
An activity chart has columns labelled "Time," "Operator," and "Machine." From 0 to 0.50 minutes, the operator is labelled "Prepare Mill" and the machine is labelled "Load Mill." From 0.50 to 2.25 minutes the operator is labelled "Idle" and the machine is labelled "Load Mill." From 2.25 to 4.50 minutes the operator is labelled "Idle" and the machine is labelled "Mill Operating (Cutting Material)." From 4.50 to 5.25 minutes the operator is labelled "Unload Mill" and the machine is labelled "Idle." All times are approximate.
B.
1
2
3
4
5
6
1
2
3
4
5
6
1
2
3
4
5
6
Time
Operator
Time
Machine
Time
Prepare Mill
Load Mill
Idle
Unload Mill
Idle
Mill
Operating
(Cutting
Material)
Idle
An activity chart has columns labelled "Time," "Operator," and "Machine." From 0 to 0.50 minutes, the operator is labelled "Prepare Mill" and the machine is labelled "Idle." From 0.50 to 2.25 minutes the operator is labelled "Load Mill" and the machine is labelled "Idle." From 2.25 to 4.50 minutes the operator is labelled "Idle" and the machine is labelled "Mill Operating (Cutting Material)." From 4.50 to 6.00 minutes the operator is labelled "Unload Mill" and the machine is labelled "Idle." All times are approximate.
C.
1
2
3
4
5
6
1
2
3
4
5
6
1
2
3
4
5
6
Time
Operator
Time
Machine
Time
Prepare Mill
Load Mill
Idle
Unload Mill
Idle
Mill
Operating
(Cutting
Material)
Idle
An activity chart has columns labelled "Time," "Operator," and "Machine." From 0 to 0.50 minutes, the operator is labelled "Prepare Mill" and the machine is labelled "Idle." From 0.50 to 2.25 minutes the operator is labelled "Load Mill" and the machine is labelled "Mill Operating (Cutting Material)." From 2.25 to 4.50 minutes the operator is labelled "Idle" and the machine is labelled "Mill Operating (Cutting Material)." From 4.50 to 5.25 minutes the operator is labelled "Unload Mill" and the machine is labelled "Idle." All times are approximate.
D.
1
2
3
4
5
6
1
2
3
4
5
6
1
2
3
4
5
6
Time
Operator
Time
Machine
Time
Prepare Mill
Load Mill
Idle
Unload Mill
Idle
Mill
Operating
(Cutting
Material)
Idle

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!