Question: Draw an activity chart for a machine operator with the following operation. The relevant times are as follows: Prepare mill for loading (cleaning, oiling, and
Draw an activity chart for a machine operator with the following operation. The relevant times are as follows:
| Prepare mill for loading (cleaning, oiling, and so on) | .50 min |
| Load mill | 1.75 min |
| Mill operating (cutting material) | 2.25 min |
| Unload mill | .75 min |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts