Question: Reducing Project Duration Crash cost ( slope ) , maximum crash time, normal time, and normal cost are provided below. The indirect costs for each

Reducing Project Duration
Crash cost (slope), maximum crash time, normal time, and normal cost are provided below. The indirect costs for each project duration are: $550(20 time units), $400(19), $350(18), $100(17), and $50(16).
\table[[Activity,\table[[Crash],[Cost],[(Slope)]],\table[[Max.],[Crash],[Time]],\table[[Normal],[Time]],\table[[Normal],[Cost]]],[A,25,1,6,70],[B,75,2,4,90],[C,0,0,5,100],[D,20,1,3,80],[E,65,3,6,100],[F,105,1,3,140],[G,40,1,6,80],[H,0,0,3,90],[I,200,1,5,210]]
Calculate the initial total cost (direct + indirect cost) before crashing the project.
1210
960
1510
1350
1670
1430
 Reducing Project Duration Crash cost (slope), maximum crash time, normal time,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!