Question: < Remaining time: 172:36 Question 1 Normal Normal Minimum Crash Cost Activity Time Cost Predecessor Time (S/day) A $50 4 $20 B 3 $60

< Remaining time: 172:36 Question 1 Normal Normal Minimum Crash Cost Activity Time Cost Predecessor Time (S/day) A $50 4 $20 B 3 $60 1 $60 C 4 $70 4 SO A D 2 $50 1 $10 A E 5 $100 $60 B 2 $90 1 $100 C G 5 $50 4 $30 D H $60 $200 2 SO E $200 F,G,H Open in Safari 2 Use the information in the table (all times are in days) to determine the optimum cost-time schedule for the project. Indirect costs for each project duration are as follows: $90 (15 time units), $70 (14), $50 (13), $40 (12), and $30 (11). Your answer: Font Size . BIUA-A-