Question: Resources Allocation and Leveling Table below presents the activities of a project. Needed Resources (man) Number Activity Duration (day) Pre-Requisite Man/day Cumulative A 5 -

Resources Allocation and Leveling

Table below presents the activities of a project.

Needed Resources (man)

Number

Activity

Duration (day)

Pre-Requisite

Man/day

Cumulative

A

5

-

1

5

B

6

A

1

6

C

7

A

1

7

D

7

C

1

7

E

17

A

1

17

F

5

E

1

5

G

11

E

1

11

H

5

F, B, D

1

5

  1. Draw Gantt Chart and Activity on Node Diagram