Question: Resources Allocation and Leveling Table below presents the activities of a project. Needed Resources (man) Number Activity Duration (day) Pre-Requisite Man/day Cumulative A 5 -
Resources Allocation and Leveling
Table below presents the activities of a project.
|
|
|
|
| Needed Resources (man) | |
| Number | Activity | Duration (day) | Pre-Requisite | Man/day | Cumulative |
| | A | 5 | - | 1 | 5 |
| | B | 6 | A | 1 | 6 |
| | C | 7 | A | 1 | 7 |
| | D | 7 | C | 1 | 7 |
| | E | 17 | A | 1 | 17 |
| | F | 5 | E | 1 | 5 |
| | G | 11 | E | 1 | 11 |
| | H | 5 | F, B, D | 1 | 5 |
- Draw Gantt Chart and Activity on Node Diagram
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
