Question: Table below presents the activities of a project. Needed Resources (man) Number Activity Duration (day) Pre-Requisite Man/day Cumulative A 5 - 1 5 B 6

Table below presents the activities of a project.

Needed Resources (man)

Number

Activity

Duration (day)

Pre-Requisite

Man/day

Cumulative

A

5

-

1

5

B

6

A

1

6

C

7

A

1

7

D

7

C

1

7

E

17

A

1

17

F

5

E

1

5

G

11

E

1

11

H

5

F, B, D

1

5

  1. Using try and error Resource Smoothing method:
    1. Draw the Daily Resources Diagram before smoothing (leveling of resources)
    2. Draw the Daily Resources Diagram after smoothing (leveling of resources)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!