Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted.The activities,immediate predecessors, and times appear in theaccompanying table:
Activity Immediate Predecessor(S)- Time (days)
A --- 3
B -- 7
C -- 2
D B 10
E A,D 5
F C 5
G E,F 12
a) The critical activities for the leadership training program development project are ____--____---____----___
b) The project length for the leadership training program developmentproject = ________ days.
c) Slack time for each of theactivities is:
Activity -----Slack Time
A---____
B----___
C----_____
D-----_____
E----______
F-----_____
G-----_____
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts