Activity Immediate Predecessor(S)- Time (days)

A --- 3

B -- 7

C -- 2

D B 10

E A,D 5

F C 5

G E,F 12

a) The critical activities for the leadership training program development project are ____--____---____----___

b) The project length for the leadership training program developmentproject = ________ days.

c) Slack time for each of theactivities is:

Activity -----Slack Time

A---____

B----___

C----_____

D-----_____

E----______

F-----_____

G-----_____

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!