Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
| Activity | Immediate Predecessor(s) | Time (days) |
| A | 2 | |
| B | 6 | |
| C | 1 | |
| D | B | 10 |
| E | A, D | 4 |
| F | C | 5 |
| G | E, F | 12 |
d) Slack time for each of the activities is: - Please show how you get slack time for A-G