Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
ACTIVITY IMMEDIATE PREDECESSORS TIMEDAYS
A
B
C
D B
E AD
F C
G EF
a what is the critical path?
b What is the total project completion time?
a Critical path is BDEG
b Total project takes days
a Critical path is ADEG
b Total project takes days
a Critical path is BDEG
b Total project takes days
a Critical path is BDEG
b Total project takes days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock