Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
ACTIVITY IMMEDIATE PREDECESSOR(S) TIME(DAYS)
A -----2
B -----5
C -----1
D B 10
E A,D 3
F C 6
G E,F 8
a. what is the critical path?
b. What is the total project completion time?
a. Critical path is BDEG
(b) Total project takes 25 days
a. Critical path is ADEG
(b) Total project takes 23 days
a. Critical path is BDEG
(b) Total project takes 26 days
a. Critical path is BDEG
(b) Total project takes 21 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!