Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity
Immediate Predecessors
Timedays
A
B
C
D
B
E
A D
F
C
G
E F
This exercise contains only part a
Part
a The correct precedence diagram for the project is shown in
Figure
Figure
Figure