Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
\table[[Activity,Immediate Predecessor(s),Time (days)],[A,-,3],[B,-,6],[C,-,1],[D,B,10],[E,A, D,4],[F,C,5],[G,E, F,10]]
This exercise contains only parts b,c, and d.
b) The critical activities for the leadership training program development project are B-D - E - G'.
c) The project length for the leadership training program development project =30 days.
d) Slack time for each of the activities is:
\table[[Activity,Slack Time],[A,13],[B,]]
Activity
Immediate Predecessor(s)
Time(days)
A
minus
3
B
minus
6
C
minus
1
D
B
10
E
A, D
4
F
C
5
G
E, F
10
This exercise contains only parts b, c, and d.
Part 2
b) The critical activities for the leadership training program development project are
B - D - E - G
.
Part 3
c) The project length for the leadership training program development project=
30 days.
Part 4
d) Slack time for each of the activities is:
Part 5
Activity
Slack Time
A
13
B
enter your response here
 Roger Ginde is developing a program in supply chain management certification

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!