Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted.
The activities, immediate predecessors, and times appear in the accompanying table:
Activity Immediate Predecessor(s) Time (days) A - 2 B - 5 C - 2 D B 10 E A, D 5 F C 5 G E, F 10
b) The critical activities for the leadership training program development project are .
c) The project length for the leadership training program development project = _? days.
d) Slack time for each of the activities is?
| Activity | Slack Time |
| A | ? |
| B | ? |
| C | ? |
| D | ? |
| E | ? |
| F | ? |
| G | ? |