Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table o o Figure 1 E Immediate Predecessor(s) Activity A B D E F G Time (days) 3 6 3 10 4 6 12 B AD EF This exercise contains only part a Figure 2 Q a) The correct precedence diagram for the project is shown in E Figure 3 a