Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activity Immediate Predecessor(s) Time (days) A - 2 B - 6 C - 1 D, B 10 E A, D 4 F C 6 G E, F 8

This exercise contains only parts b, c, and d.

b) The critical activities for the leadership training program development project are ______?

c) The project length for the leadership training program development project = ____?

d) Slack time for each of the activities is:

Activity

Slack Time

A

_____?

B.

____________?

C

_________?

D

________?

E.

_______?

F

_______?

G

_______?

note: Relationship for slack time is: Slackx=(Late FinishxEarly Finishx) or Late (StartxEarly Startx)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!