Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity Immediate Predecessor(s) Time (days) A - 2 B - 6 C - 1 D, B 10 E A, D 4 F C 6 G E, F 8
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are ______?
c) The project length for the leadership training program development project = ____?
d) Slack time for each of the activities is:
| Activity | Slack Time |
| A | _____? |
| B. | ____________? |
| C | _________? |
| D | ________? |
| E. | _______? |
| F | _______? |
| G | _______? |
note: Relationship for slack time is: Slackx=(Late FinishxEarly Finishx) or Late (StartxEarly Startx)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts