Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activity

Immediate Predecessor(s)

Time (days)

A

minus

2

B

minus

5

C

minus

1

D

B

10

E

A, D

3

F

C

6

G

E, F

8

b) The critical activities for the leadership training program development project are __________.

c) The project length for the leadership training program development project = ______ days.

d) Slack time for each of the activities is: Activity Slack Time A, B, C, D, E, F, G.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!