Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
| Activity | Immediate Predecessor(s) | Time (days) |
| A | minus | 2 |
| B | minus | 5 |
| C | minus | 1 |
| D | B | 10 |
| E | A, D | 3 |
| F | C | 6 |
| G | E, F | 8 |
b) The critical activities for the leadership training program development project are __________.
c) The project length for the leadership training program development project = ______ days.
d) Slack time for each of the activities is: Activity Slack Time A, B, C, D, E, F, G.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts