Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
| Activity | Immediate Predecessor(s) | Time (days) |
| A | 3 | |
| B | 5 | |
| C | 3 | |
| D | B | 10 |
| E | A, D | 3 |
| F | C | 5 |
| G | E, F | 8 |
1.) The critical activities for the leadership training program development project = B - D - E - G
2.) The project length for the leadership training program development project = 2626 days.
3.) Slack time for each of the activities is:
A:
B:
C:
D:
E:
F:
G:
Find the slack time for items A through G
Step by Step Solution