Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A 3 B 7 C 2 D B 10 E A, D 5 F C 5 G E, F 10 This exercise contains only parts b, c, and d. Part 2 b) The critical activities for the leadership training program development project are B - D - E - G . Part 3 c) The project length for the leadership training program development project = 3232 days. Part 4 d) Slack time for each of the activities is:
Activity Slack Time A
enter your response here