Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 3 B A 4 C A 9 D B 2 E

Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 4
C A 9
D B 2
E C%media:cm.png% D 7
F D 3
G F 4
H E%media:cm.png% G 5
What is the critical path?
multiple choice 1
A-C-E-H
A-B-D-E-H
A-B-D-F-G-H
A-C-E-F-G-H
How many weeks will it take to complete the project?
Which activities have slack, and how much?
multiple choice 2
Bcm 3 weekssc Ccm 2 weekssc Fcm 1 weeksc Hcm 2 weeks.
Bcm 3 weekssc Dcm 3 weekssc Fcm 3 weekssc Gcm 3 weeks.
Bcm 2 weekssc Ccm 3 weekssc Ecm 4 weekssc Hcm 1 week.