Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 1 B A 4 C A 3 D B 2 E
Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D B
E C D
F D
G F
H E G
What is the critical path?
multiple choice
ACDFG
ACEH
ABDEH
ABDFGH
How many weeks will it take to complete the project?
Which activities have slack, and how much?
multiple choice
C weeks; F week; and G week.
B weeks; D week; and E week.
D weeks; G week; and H week.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
