Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) m DOOD C%media:cm.png% miem E%media:cm.png% I b. What is the critical path? O A-B-D-F-G-H

Schedule the following activities using CPM:Schedule the following activities using CPM:

Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) m DOOD C%media:cm.png% miem E%media:cm.png% I b. What is the critical path? O A-B-D-F-G-H O A-B-D-E-H O A-C-D-F-G-H O A-B-D-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? OC. 4 weeks: F. 2 weeks : G. 2 weeks. OB. 3 weeks iH2 weeks ;F. 1 week. OB. 1 week :C, 3 weeks : F2 weeks