Question: Schedule the following activities using CPM: Activity Immediate Predecessor Time (weeks) A - 2 B a 3 C a 5 D b 4 E c,d
Schedule the following activities using CPM:
Activity Immediate Predecessor Time (weeks)
A - 2
B a 3
C a 5
D b 4
E c,d 7
F d 2
G f 3
H e,g 7
a. What is the critical path?
b. How many weeks will it take to complete the project?
c. Which activities have slack, and how much?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
