Question: Schedule the following activities using CPM: Activity Immediate Predecessor Time (weeks) A - 8 B a 4 C a 4 D b 8 E c,d

Schedule the following activities using CPM:

Activity Immediate Predecessor Time (weeks)

A - 8

B a 4

C a 4

D b 8

E c,d 2

F d 6

G f 2

a. What is the critical path?

b. How many weeks will it take to complete the project?

c. Which activities have slack, and how much?