Question: Schedule the following activities using CPM: Activity Immediate Predecessor Time (weeks) A - 8 B a 4 C a 4 D b 8 E c,d
Schedule the following activities using CPM:
Activity Immediate Predecessor Time (weeks)
A - 8
B a 4
C a 4
D b 8
E c,d 2
F d 6
G f 2
a. What is the critical path?
b. How many weeks will it take to complete the project?
c. Which activities have slack, and how much?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
