Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 5 D B 4 E C D
Schedule the following activities using CPM:
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 3 | |
| B | A | 4 |
| C | A | 5 |
| D | B | 4 |
| E | C D | 8 |
| F | D | 6 |
| G | F | 4 |
| H | E G | 5 |
b. What is the critical path?
multiple choice 1
A-C-E-F-G-H
A-B-E-H
A-B-D-F-G-H
A-B-D-E-H
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?
multiple choice 2
E 1 week H 2 weeks.
C 5 weeks E 2 weeks.
B 1 week D 3 weeks.