Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 4 C A 5 D B 4 E C D

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 4
C A 5
D B 4
E C

D
8
F D 6
G F 4
H E

G
5

b. What is the critical path?

multiple choice 1

A-C-E-F-G-H

A-B-E-H

A-B-D-F-G-H

A-B-D-E-H

c. How many weeks will it take to complete the project?

d. Which activities have slack, and how much?

multiple choice 2

E 1 week H 2 weeks.

C 5 weeks E 2 weeks.

B 1 week D 3 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!