Question: Schedule the following activities using CPM: Activity Immediate Predecessor Time (Weeks) A - 1 B A 4 C A 3 D B 2 E C,
Schedule the following activities using CPM:
| Activity | Immediate Predecessor | Time (Weeks) |
| A | - | 1 |
| B | A | 4 |
| C | A | 3 |
| D | B | 2 |
| E | C, D | 5 |
| F | D | 2 |
| G | F | 2 |
| H | E, G | 3 |
- Draw the network
- What is the critical path?
- How many weeks will it take to complete the project?
- Which activities have slack, and how much?