Question: Schedule the following activities using CPM: b. What is the critical path? A-B-D-F-G-H A-C.E-F-G-H A-C-E-H A.B-D.E.H c. How many weeks will it take to complete

Schedule the following activities using CPM: b.
Schedule the following activities using CPM: b. What is the critical path? A-B-D-F-G-H A-C.E-F-G-H A-C-E-H A.B-D.E.H c. How many weeks will it take to complete the project? d. Which activities have slack, and how much? B. 2 weeks: D.1 weeki E14 weeks. A, 4 weeks: B,1 weeki D,2 weeks: C. 2 weeksi F,2 weeks; G,2 weeks