Question: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 3 B A 4 C A 9 D B 2 E C , D 7 F D

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 3
B A 4
C A 9
D B 2
E C, D 7
F D 3
G F 4
H E, G 5
Schedule the following activities using CPM:
b. What is the critical path?
A-C-E-H
A-B-D-F-G-H
A-C-E-F-G-H
A-B-D-E-H
c. How many weeks will it take to complete the project?
Number of weeks:
d. Which activities have slack, and how much?
B,3 weeks; C,2 weeks; F,1 week; H,2 weeks.
B,2 weeks; C,3 weeks; E,4 weeks; H,1 week.
B,3 weeks; D,3 weeks; F,3 weeks; G,3 weeks.