Question: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 3 B A 4 C A 9 D B 2 E C , D 7 F D
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D B
E C D
F D
G F
H E G
Schedule the following activities using CPM:
b What is the critical path?
ACEH
ABDFGH
ACEFGH
ABDEH
c How many weeks will it take to complete the project?
Number of weeks:
d Which activities have slack, and how much?
B weeks; C weeks; F week; H weeks.
B weeks; C weeks; E weeks; H week.
B weeks; D weeks; F weeks; G weeks.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
