Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,\table[[TIME],[(WEEKS)]]],[A,-,4],[B,A,3],[C,A,6],[D,B,7],[E,Comedia: cm.png%,3],[F,D,5],[G,D,4],[H,F,2]]
b. What is the critical path?
A-B-D-E-H
A-C-E-F-G-H
A-C-E-G-H
A-B-D-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks
d. Which activities have slack. and how much?
Schedule the following activities using CPM: \