Using the priority list T6, T5, T7, T4, T1, T9, T3, T8, T2, schedule the project below w Task Time Required Tasks that must be completed first FNPNPPFE T1 T2 T3 T4 T5 T6 T7 T8 T9 6 8 10 3 6 6 3 7 10 T1, T2 T2 T2, T3 T4 T4, T5 T5, T6 Task 7 is done by [Select an answer starting at time Submit Question Task 8 is done by Select an answer starting at time The finishing time for the schedule is