Question: Suppose a set up time for an operation is 2 hours and unit processing time is 4 minutes. What is the unit operation time if;
Suppose a set up time for an operation is 2 hours and unit processing time is 4 minutes. What is the unit operation time if;
a) The lot size is 50 units? (3 points)
b) The lot size is 500 units? (3 points)
c) What are the 2 benefits of reduced set up time? (4 points)