Question: Suppose that a task in a project has the following time estimates: to= optimistic completion time = 6 weeks tm= most likely completion time =
to = optimistic completion time = 6 weeks
tm = most likely completion time = 8 weeks
tp = pessimistic completion time = 11 weeks
Compute the expected task variance.