Question: Suppose you have a four-activity sequential process. Throughput capacities are shown in parentheses: Task 1 (6) ---> Task 2 (5) ---> Task 3 (4) --->
Suppose you have a four-activity sequential process. Throughput capacities are shown in parentheses:
Task 1 (6) ---> Task 2 (5) ---> Task 3 (4) ---> Task 4 (6).
No buffers exist between tasks, so an upstream task must wait if the downstream task is busy.
Use this information to answer the next 3 questions.
1) What is the actual throughput rate out of task 4? Pick the closest answer.
A) 1
B) 2
C) 3
D) 4
E) 5
F) 6
2) What is the utilization for task 1? Pick the closest answer.
A) 10%
B) 25%
C) 33%
D) 50%
E) 66%
F) 75%
G) 90%
3) Which task(s) would be blocked? Check all that apply.
A) 1
B) 2
C) 3
D) 4
E) 5