Question: Suppose you have a four-activity sequential process. Throughput capacities are shown in parentheses: Task 1 (6) ---> Task 2 (5) ---> Task 3 (4) --->
Suppose you have a four-activity sequential process. Throughput capacities are shown in parentheses:
Task 1 (6) ---> Task 2 (5) ---> Task 3 (4) ---> Task 4 (6).
No buffers exist between tasks, so an upstream task must wait if the downstream task is busy.
Use this information to answer the next 3 questions.
What is the actual throughput rate out of task 4? Pick the closest answer.
a. 1
b. 2
c. 3
d. 4
e. 5
f. 6
2. What is the utilization for task 1? Pick the closest answer.
a. 10%
b. 25%
c. 33%
d. 50%
e. 66%
f. 75%
g. 90%
3. Which task(s) would be blocked? Check all that apply.
a. 1
b. 2
c. 3
d. 4
e. 5
Step by Step Solution