Question: Suppose you have a four-activity sequential process. Throughput capacities are shown in parentheses: Task 1 (6) ---> Task 2 (5) ---> Task 3 (4) --->
Suppose you have a four-activity sequential process. Throughput capacities are shown in parentheses:
Task 1 (6) ---> Task 2 (5) ---> Task 3 (4) ---> Task 4 (6).
No buffers exist between tasks, so an upstream task must wait if the downstream task is busy.
Use this information to answer the next 2 questions.
What is the actual throughput rate out of task 4? Pick the closest answer.
A. 1
B. 2
C. 3
D. 4
E. 5
F. 6
What is the utilization for task 1? Pick the closest answer.
A. 0%
B. 10%
C. 25%
D. 33%
E. 50%
F. 66%
G. 75%
Suppose you are given the flowchart shown below (Task 5 requires input from both Task 2 and Task 4). There are no buffers between tasks. The numbers in parentheses reflect throughput capacities. Using this, answer the next 3 questions:
Task 1 (8) ------------> Task 2 (10) ------------| |------> Task 5 (18) -----------> Task 3 (15) ------------> Task 4 (9)-------------|
What is the actual throughput out of task 5?
A. Less than 8
B. 8
C. 9
D. 10
E. 15
F. 18
Which task(s) would be blocked? Check all that apply.
A. Task 1
B. Task 2
C. Task 3
D. Task 4
E. Task 5
Which task(s) would be starved? Check all that apply.
A. Task 1
B. Task 2
C. Task 3
D. Task 4
E. Task 5