Question: Table 7.5 Activity Predecessor Time (days) A -- 8 B -- 6 C -- 3 D A,B 10 E C 8 F A 5 G
Table 7.5 Activity Predecessor Time (days) A -- 8 B -- 6 C -- 3 D A,B 10 E C 8 F A 5 G D,E 3 H G 4 Using Table 7.5, what is the earliest that activity D can be finished Question 6 options: 18 days 13 days 25 days 8 days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
