Question: Table 7.5 Activity Predecessor Time (days) A -- 8 B -- 6 C -- 3 D A,B 10 E C 8 F A 5 G
Table 7.5 Activity Predecessor Time (days) A -- 8 B -- 6 C -- 3 D A,B 10 E C 8 F A 5 G D,E 3 H G 4 Using Table 7.5, what is the earliest completion time of this project? Question 5 options: 25 days 29 days 23 days 27 days