Question: table [ [ Activity ID , Duration ( in days ) , Predecessor ] , [ A , 5 , - ] , [

\table[[Activity ID,Duration (in days),Predecessor],[A,5,-],[B,4,A],[C,5,A],[D,6,B],[E,3,C],[F,4,D, E]]
1.1. Complete the forward and backward pass. [13]
1.2. Compute the ES, EF, LS and LF times for each activity. [5]
1.3. Compute the activity slack for each activity.[3]
1.4. Identify the critical path. [2]
1.5. How many days will the project take to complete? [2]
Question 2
[15 marks]
The project life cycle typically passes sequentially through four (4) stages. With aid of diagram Briefly describe the stages of the project life cycle.
Question 3
[10 marks]
Describe the five (5) major characteristics of a project.
 \table[[Activity ID,Duration (in days),Predecessor],[A,5,-],[B,4,A],[C,5,A],[D,6,B],[E,3,C],[F,4,D, E]] 1.1. Complete the forward and backward

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!